- videbaks's home page
- Posts
- 2024
- 2023
- 2022
- 2021
- 2020
- 2019
- 2018
- December (1)
- November (2)
- October (1)
- September (1)
- August (1)
- July (4)
- April (3)
- March (1)
- February (2)
- January (1)
- 2017
- 2016
- November (1)
- September (2)
- August (2)
- July (1)
- June (1)
- May (1)
- April (1)
- March (1)
- February (1)
- January (1)
- 2015
- 2014
- 2013
- 2012
- 2011
- 2010
- November (3)
- 2009
- My blog
- Post new blog entry
- All blogs
iTPC closeout review preparations
4/25 uploaded overview talk after walk tru this morning
I am starting the prep's for the review. This will be used to post internal documents and links.
The indico page is at https://indico.bnl.gov/event/5980/
where documents will be posted.
The draft agenda is
Agenda
(Note is is shifted by 1/2 hour for indico as requested)
· 8:30 (30) executive session
· 9:00 (20+10) Project overview (Videbaek)
o Status/updates since last review
o Deliverables
o Management, safety
o Cost
o schedule
· 9:30 (15+5) MWPC status and KPP verification (Q.Xu)
· 9:50 (15+5) Electronics status and KPP ( Tonko)
· 10:10 (15+5) Software progress (Irakli)
· 10:30 (20+10) Commissioning and run progress (D.Cebra)
· 11:00 (20+10) Summary (F. Videbaek)
o Overall assessment
o Transition to ops
· 11:30 (30) Questions and discussion to all talks
· 12:00 (120-180) executive session
· Between 14:00-15:00 closeout
Documents
· Quarterly reports
· Reports from previous review and response
· Draft closeout, , KPP report, transitions to ops (single document)
· lessons learned document
· Links to previous reviews