STAR Technical Support Group

On this site you'll be able to:

 

 

Electronics Lab private network

 

Plan Overview:
 

In Room 1-232 (the "Electronics Lab"), our goal is to remove experimental test equipment and unsupported (or poorly supported) computer systems from the "public" network.   These are likely sources of Cyber Security concerns and may benefit from a less volatile network environment than the campus network.  To do this, we will create a private network in the Electronics Lab, with one maintained Linux node that will be dual-homed on the public network to act as a gateway to access the private network as needed.   With the introduction of one (or more) Linux box(es), eventually we hope to retire the old Sun workstation completely.

The address space we will use is 192.168.140.0/255.255.255.0 (256 IP addresses).  This is "registered" with ITD network operations as a STAR private network, so that if anything "escapes" from the private space into the campus network, they will know who to call.

Given the short list of anticipated devices (below), no name server is planned, nor other common network services such as DHCP (subject to change as needed). 

Devices Using This Network:

  1. The Linux gateway system -- presley.star.bnl.gov (Scientific Linux 4.5) using 192.168.140.1
  2. One Sun Ultra E450 -- "svtbmonitor" (Solaris 8) using 192.168.140.2 
  3. One serial console server using 192.168.140.3 
  4. Several (~4-5) rack-mounted MVME or similar devices at any time.  An initial set have been assigned 192.168.140.11-15.  A set of working sample boot parameters are included in a file attached to this page (see the links in the Attachments section below).
  5. Update August 4, 2009:  Six more processors are being added to the network.  The name trgfe6 through trgfe11 have been assigned 192.168.140.16-21 (ie. added to /etc/hosts on presley and svtbmonitor).
  6. Several Windows PC's, including laptops that may come and go (which will require manual configuration -- a small inconvenience that can perhaps be overcome with networking "profile" software that stores multiple configurations on the node -- to be investigated, such as http://www.eusing.com/ipswitch/free_ip_switcher.htm

Status:

A Linux box named presley.star.bnl.gov is configured on the public network, with a second NIC using 192.168.140.1 to act as a manual gateway node as needed.  It is in the south-west corner of the lab.  An account named daqlab has been created (contact Wayne or Danny for the password if appropriate)

 

For the effort to replace svtbmonitor,  the home directory of svtbmonitor's testlab account have been copied over to presley in /home/svtbmonitor/testlab. 

Danny and Phil identified a handful of files from svtbmonitor as important so far:

  • emc.tcl
  • smd_qa.tcl
  • tower_qaodt.tcl
  • grab (compiled C code to open a window and connect to a specified node on the serial console server)
  • grab.bag (used by grab to "resolve" common names into ports on the console server)

The original versions of these files are all in their original (relative) paths, and modified versions for presley and the current networking setup were created and put in /home/daqlab/.  The Tcl scripts were modified to account for the slightly different environment on presley and were demonstrated to work (at least the basics - still needs testing to confirm full functionality).  The "grab" executable had to be recompiled from source (simple enough - the required source code consists of "grab.c" and only required a single minor change for the new environment on presley).  So far so good there.

 

Two small "desktop" 10/100 Mbps switches have been connected to each other to serve as the "backbone":

  • one is on a shelf on the west wall
  • the other is on a shelf on the north wall

 

This is easy to expand with one or two 16-port switches if needed (well, it actually is needed as I write this...).  (In fact, these switches have been rather fluid in the first months, coming and going and being swapped for others, all at a slight inconvenience to those of us trying to work with them...)

[Feb. 19, 2009 update -- the physical layout of switches and cables has been switched around many times since this description and I don't know the current state.]

The old networking (not to mention the serial lines) is a mess of cables, old hubs and switches that I plan to ignore as long as possible, though most should be removed if it isn't nailed down.  [Feb. 19, 2009 - some clean up appears to have been done by the folks working in the lab.]

 

To Be Done, moving from svtbmonitor to presley (last updated, Feb 19, 2009):

Towards this end we've identified the following remaining tasks:

Configure backups of the home directories on presley as another safety net for the critical content from svtbmonitor that has been transferred over.

Jack Engelage and Hank Crawford have transferred a bunch of files from svtbmonitor to presley [are they done?].  A "trigger" group was created containing Jack, Chris and Hank.  They have /home/trigger to share amongst themselves.

The biggies: 

VxWorks compilers for Linux and booting the VME processors from presley.  [Feb 19, 2009 update:  Yury Gorbunov (and Jack Engelage?) have made successful boots of trgfe3 from presley via FTP, so it looks like svtbmonitor has a chance of being retired at some point.  Sample boot parameters are attached]

 

Ralph test area

This is my first test page.

Shutdown schedule

FY04

Project Start Date: Fri 1/2/04
Project Finish Date: Mon 10/25/04

STAR FY04 v3 Shutdown


ID
Name
DurationStart_DateFinish_DateResource_NamesPredecessorsSuccessors
1
STAR Detector Operations
211.35 daysMon 1/5/04Mon 10/25/04   
2
Physics Run FY04
96 daysMon 1/5/04Sat 5/15/04  5FF
3
Start Shutdown Activities
116.35 daysSat 5/15/04Mon 10/25/04   
4
Move Detector into AB
14.6 daysSat 5/15/04Thu 6/3/04   
5
Purge TPC Gas
1 daySat 5/15/04Sat 5/15/04 2FF6SS
6
Subsystem Testing
6 daysSat 5/15/04Fri 5/21/04 5SS7
7
Retract PMD Detector
0.1 daysMon 5/24/04Mon 5/24/04Mech.Tech.68
8
Remove East BBC Detector
0.25 daysMon 5/24/04Mon 5/24/04Mech.Tech.79
9
Retract East Pole Tip
0.5 daysMon 5/24/04Mon 5/24/04Mech.Tech.[2]810FF
10
Install Scaffold
0.25 daysMon 5/24/04Mon 5/24/04Carpenter[2]9FF12,11
11
Remove Shield Wall
2.5 daysMon 5/24/04Thu 5/27/04Riggers[3]1026,23,16SS,18,135
12
Remove West Pole Tip Utilities
0.25 daysMon 5/24/04Tue 5/25/04Mech.Tech.1013
13
Remove West BBC Detector
0.25 daysTue 5/25/04Tue 5/25/04Mech.Tech.1214
14
Retract West Pole Tip
0.5 daysTue 5/25/04Tue 5/25/04Mech.Tech.[2]1315FF
15
Install Scaffold
0.13 daysTue 5/25/04Tue 5/25/04Carpenter[2]14FF 
16
Disconnect Electrical Power
0.5 daysMon 5/24/04Tue 5/25/04Electrician[2]11SS18,17
17
Disconnect Magnet Power
0.5 daysTue 5/25/04Tue 5/25/04Elect.Tech.[2]1618
18
Remove Buss Bridge
0.25 daysThu 5/27/04Thu 5/27/04Mech.Tech.[2]16,17,1119,21
19
Disconnect Platform MCWS
0.5 daysThu 5/27/04Fri 5/28/04Mech.Tech.1820
20
Disconnect Subsystems Utilities
1 dayFri 5/28/04Mon 5/31/04Mech.Tech.1926
21
Remove Platform Bridge
0.25 daysThu 5/27/04Thu 5/27/04Mech.Tech.[2]1826,22
22
Remove South Platform Stairs
0.25 daysThu 5/27/04Fri 5/28/04Mech.Tech.[2]2126,24
23
Disconnect RHIC Vacuum Pipe
0.5 daysThu 5/27/04Thu 5/27/04Mech.Tech.11 
24
Remove Seismic Anchors
0.25 daysFri 5/28/04Fri 5/28/04Mech.Tech.[2]2225
25
Disconnect Magnet LCW
0.25 daysFri 5/28/04Fri 5/28/04Mech.Tech.[2]2426
26
Roll Detector into AB
1 dayMon 5/31/04Tue 6/1/04Mech.Tech.[2]11,21,22,25,2027
27
Blow-out Magnet Coils
0.5 daysTue 6/1/04Tue 6/1/04Mech.Tech.[2]2628
28
Connect South Platform Stairs
0.5 daysTue 6/1/04Wed 6/2/04Mech.Tech.[2]2729
29
Connect Platform Bridge
0.5 daysWed 6/2/04Wed 6/2/04Mech.Tech.[2]2831,30
30
Connect Seismic Anchors
0.5 daysWed 6/2/04Thu 6/3/04Mech.Tech.29 
31
Install Buss Bridge
0.5 daysWed 6/2/04Thu 6/3/04Mech.Tech.[2]2932
32
Connect Electrical Power
0.5 daysThu 6/3/04Thu 6/3/04Electrician[2]3133SS
33
Connect Subsystems Utilities
0.5 daysThu 6/3/04Thu 6/3/04Mech.Tech.32SS34SS
34
Connect Platform MCWS
0.5 daysThu 6/3/04Thu 6/3/04Mech.Tech.33SS35
35
Detector In AB
0 daysThu 6/3/04Thu 6/3/04 3437,117,121
36
Remove East & West FTPC
13.75 daysThu 6/3/04Wed 6/23/04   
37
Remove E/W IFC Air Manifolds
0.25 daysThu 6/3/04Thu 6/3/04Mech.Tech.3538
38
Remove East & West Scaffold
0.5 daysThu 6/3/04Fri 6/4/04Carpenter[2]3739
39
Install West Platform & Rails
1 dayFri 6/4/04Mon 6/7/04Carpenter[2]3840,41
40
Remove West FTPC
0.5 daysMon 6/7/04Mon 6/7/04Mech.Tech.3945
41
Rig Installation Frame into AB
0.5 daysMon 6/7/04Mon 6/7/04Riggers[3]3942SS
42
Install East Installation Frame
0.5 daysMon 6/7/04Mon 6/7/04Mech.Tech.[2]41SS43
43
Install East Rails
1 dayMon 6/7/04Tue 6/8/04Mech.Tech.[2]4244
44
Remove East FTPC
0.5 daysTue 6/8/04Wed 6/9/04Mech.Tech.[2]4345
45
East & West FTPC's Removed
0 daysWed 6/9/04Wed 6/9/04 40,4446,48
46
Maintenance on FTPC's
10 daysWed 6/9/04Wed 6/23/04Electronic Tech45 
47
Remove Cone
11.5 daysWed 6/9/04Thu 6/24/04   
48
Disconnect Utilities
4 daysWed 6/9/04Tue 6/15/04Mech.Tech.4549
49
Remove Cone from IFC
0.5 daysTue 6/15/04Tue 6/15/04Mech.Tech.4876,126
50
Remove East Installation Frame
1 dayTue 6/22/04Wed 6/23/04Mech.Tech.[2]76,12651FF
51
Remove Installation Frame from AB
0.5 daysWed 6/23/04Wed 6/23/04Riggers[3]50FF52
52
Remove Installation Frame West
1 dayWed 6/23/04Thu 6/24/04Carpenter[2]5153
53
Cone Removed
0 daysThu 6/24/04Thu 6/24/04 5257
54
Install East BEMC Modules
47.5 daysMon 6/14/04Wed 8/18/04   
55
(30) Modules Delivered
4 daysMon 6/14/04Fri 6/18/04Riggers[3]57FF-5 days56FF
56
(30) Modules Staged in AB
4 daysMon 6/14/04Fri 6/18/04Mech.Tech.[2]55FF 
57
Install East & West Scaffold
0.5 daysThu 6/24/04Fri 6/25/04Carpenter[2]5358,55FF-5 days
58
Remove East Side Cables & Tray
3 daysFri 6/25/04Wed 6/30/04Mech.Tech.[2]5759
59
Erect Installation Fixture S.E. Upper
0.5 daysWed 6/30/04Wed 6/30/04Mech.Tech.[2]5860
60
Remove S.E. TPC Support Arm
0.25 daysWed 6/30/04Thu 7/1/04Mech.Tech.[2]5961
61
Install Modules 106-103
4 daysThu 7/1/04Wed 7/7/04Mech.Tech.[2]6062
62
Erect Installation Fixture S.E. Lower
0.5 daysWed 7/7/04Wed 7/7/04Mech.Tech.[2]6163
63
Install Modules 102-89
14 daysWed 7/7/04Tue 7/27/04Mech.Tech.[2]6264
64
Install S.E. TPC Support Arm
0.5 daysTue 7/27/04Wed 7/28/04Mech.Tech.[2]6365
65
Erect Installation Fixture N.E. Lower
0.5 daysWed 7/28/04Wed 7/28/04Mech.Tech.[2]6466
66
Install Modules 77-88
12 daysWed 7/28/04Fri 8/13/04Mech.Tech.[2]6567
67
Remove Installation Fixture
0.25 daysFri 8/13/04Fri 8/13/04Mech.Tech.[2]6668
68
Install East Side Cables & Tray
3 daysFri 8/13/04Wed 8/18/04Mech.Tech.[2]6769
69
East BEMC Installation Complete
0 daysWed 8/18/04Wed 8/18/04 6882,72
70
Install BEMC PMT Boxes
35 daysWed 7/14/04Wed 9/1/04   
71
Install 208 VAC Power
15 daysWed 7/14/04Wed 8/4/04Electrician[2]72SF-10 days 
72
Install PMT Boxes
10 daysWed 8/18/04Wed 9/1/04Mech.Tech.[2]6973FF,71SF-10 days
73
Install Electronics
20 daysWed 8/4/04Wed 9/1/04Electronic Tech72FF74
74
PMT Box Installation Complete
0 daysWed 9/1/04Wed 9/1/04 73144
75
Install SSD
20.5 daysTue 6/15/04Wed 7/14/04   
76
Rig Cone to Cleanroom Roof
0.5 daysTue 6/15/04Wed 6/16/04Mech.Tech.4977,50
77
Install SSD on Cone
20 daysWed 6/16/04Wed 7/14/04Mech.Tech.7678SS,80
78
Install LV Crate & Cables
5 daysWed 6/16/04Wed 6/23/04Electronic Tech77SS79
79
Install RDO Boxes
5 daysWed 6/23/04Wed 6/30/04Electronic Tech78 
80
SSD Installed on Cone
0 daysWed 7/14/04Wed 7/14/04 7785
81
Install Cone
20.5 daysWed 8/18/04Thu 9/16/04   
82
Rig Installation Frame into AB
0.5 daysWed 8/18/04Thu 8/19/04Riggers[3]6983SS
83
Install East Installation Frame
0.5 daysWed 8/18/04Thu 8/19/04Mech.Tech.[2]82SS84
84
Install Tables & Rails
0.5 daysThu 8/19/04Thu 8/19/04Mech.Tech.8385
85
Rig Cone to Rails
0.5 daysThu 8/19/04Fri 8/20/04Mech.Tech.[2]84,8086
86
Survey SSD to SVT
2 daysFri 8/20/04Tue 8/24/04Surveyors[2]8587
87
Complete SSD Installation
2 daysTue 8/24/04Thu 8/26/04Mech.Tech.8688
88
Test Utility Connections
1 dayThu 8/26/04Fri 8/27/04Electronic Tech8789FF
89
Clean TPC IFC
1 dayThu 8/26/04Fri 8/27/04Mech.Tech.88FF90
90
Install Cone in Detector
0.5 daysFri 8/27/04Fri 8/27/04Mech.Tech.8991
91
Test IFC High Voltage
0.5 daysFri 8/27/04Mon 8/30/04Electronic Tech9092
92
Survey TPC to Magnet
2 daysMon 8/30/04Wed 9/1/04Surveyors[2]9193
93
Survey SVT to TPC
2 daysWed 9/1/04Fri 9/3/04Surveyors[2]9294
94
Install East Partitions
0.5 daysFri 9/3/04Fri 9/3/04Mech.Tech.93110
95
Connect Water Lines
0.5 daysMon 9/6/04Tue 9/7/04Mech.Tech.11096
96
Connect RDO Cables
1 dayTue 9/7/04Wed 9/8/04Electronic Tech9597
97
Remove East Rails from IFC
0.5 daysWed 9/8/04Wed 9/8/04Mech.Tech.[2]9698
98
Remove East Installation Frame
0.5 daysWed 9/8/04Thu 9/9/04Mech.Tech.[2]9799FF
99
Remove Installation Frame from AB
0.25 daysThu 9/9/04Thu 9/9/04Riggers[3]98FF100
100
East Side Complete
0 daysThu 9/9/04Thu 9/9/04 99107,101
101
Install West Partitions
0.5 daysThu 9/9/04Thu 9/9/04Mech.Tech.100112
102
Connect Water Lines
0.5 daysMon 9/13/04Mon 9/13/04Mech.Tech.114103
103
Connect RDO Cables
1 dayMon 9/13/04Tue 9/14/04Electronic Tech102104
104
Remove West Rails from IFC
0.5 daysTue 9/14/04Wed 9/15/04Mech.Tech.103105
105
Remove Installation Frame West
1 dayWed 9/15/04Thu 9/16/04Carpenter[2]104106
106
West Side Complete
0 daysThu 9/16/04Thu 9/16/04 105107
107
Cone Installation Complete
0 daysThu 9/16/04Thu 9/16/04 100,106144
108
Install FTPC East & West in AB
12.5 daysWed 8/25/04Mon 9/13/04   
109
Run & Test N. Platform
5 daysWed 8/25/04Wed 9/1/04Electronic Tech110SF-2 days 
110
Install East FTPC in Detector
1 dayFri 9/3/04Mon 9/6/04Mech.Tech.[2]94115,109SF-2 days,95
111
Run & Test N. Platform
5 daysWed 9/1/04Wed 9/8/04Electronic Tech114SF-2 days 
112
Remove West Scaffold
0.25 daysThu 9/9/04Fri 9/10/04Carpenter[2]101113
113
Install West Platform & Rails
0.25 daysFri 9/10/04Fri 9/10/04Carpenter[2]112114
114
Install West FTPC in Detector
1 dayFri 9/10/04Mon 9/13/04Mech.Tech.[2]113115,111SF-2 days,102
115
FTPC Installed in AB
0 daysMon 9/13/04Mon 9/13/04 114,110 
116
PMD Maintenance
40 daysThu 6/3/04Thu 7/29/04   
117
Subsystem Maintenance
30 daysThu 6/3/04Thu 7/15/04 35118
118
Detector Commisioning
10 daysThu 7/15/04Thu 7/29/04 117119
119
PMD Maintenance Complete
0 daysThu 7/29/04Thu 7/29/04 118 
120
EEMC Maintenance
90 daysThu 6/3/04Thu 10/7/04   
121
Maintenance
50 daysThu 6/3/04Thu 8/12/04 35122SS
122
MAPMT Installation
80 daysThu 6/3/04Thu 9/23/04Mech.Tech.[2]121SS123
123
Subsystem Testing
10 daysThu 9/23/04Thu 10/7/04 122124
124
EEMC Maintenance Complete
0 daysThu 10/7/04Thu 10/7/04 123 
125
TPC Maintenance
50 daysTue 6/15/04Tue 8/24/04   
126
Repair IFC Strip Short
5 daysTue 6/15/04Tue 6/22/04Mech.Tech.49127,50,131SS
127
Modify Resistor Chain
5 daysTue 6/22/04Tue 6/29/04Mech.Tech.126128
128
FEE & RDO Maintenance
40 daysTue 6/29/04Tue 8/24/04Electronic Tech127129
129
TPC Maintenance Complete
0 daysTue 8/24/04Tue 8/24/04 128 
130
TOF Maintenance
15 daysTue 6/15/04Tue 7/6/04   
131
Tray Maintenance
10 daysTue 6/15/04Tue 6/29/04 126SS132
132
Detector Testing
5 daysTue 6/29/04Tue 7/6/04 131133
133
TOFp Maintenance Complete
0 daysTue 7/6/04Tue 7/6/04 132 
134
FPD Installation
20 daysThu 5/27/04Thu 6/24/04   
135
Install West Detectors
10 daysThu 5/27/04Thu 6/10/04Mech.Tech.11136
136
Install N. E. Stand for 20-cm Travel
5 daysThu 6/10/04Thu 6/17/04Mech.Tech.[2]135137
137
Detector Commisioning
5 daysThu 6/17/04Thu 6/24/04 136138
138
FPD Installation Complete
0 daysThu 6/24/04Thu 6/24/04 137140
139
BBC Maintenance
15 daysThu 6/24/04Thu 7/15/04   
140
Subsystem Maintenance
10 daysThu 6/24/04Thu 7/8/04 138141
141
Detector Commisioning
5 daysThu 7/8/04Thu 7/15/04 140142
142
BBC Maintenance Complete
0 daysThu 7/15/04Thu 7/15/04 141 
143
Move Detector into WAH
27 daysThu 9/16/04Mon 10/25/04   
144
Disconnect Electrical Power
0.5 daysThu 9/16/04Thu 9/16/04Electrician[2]107,74147,145SS,146SS
145
Disconnect Platform MCWS
0.5 daysThu 9/16/04Thu 9/16/04Mech.Tech.144SS 
146
Disconnect TPC Utilities
0.5 daysThu 9/16/04Thu 9/16/04Mech.Tech.144SS 
147
Remove Buss Bridge
0.5 daysThu 9/16/04Fri 9/17/04Mech.Tech.[2]144148
148
Remove Platform Bridge
0.5 daysFri 9/17/04Fri 9/17/04Mech.Tech.[2]147149
149
Remove South Platform Stairs
1 dayFri 9/17/04Mon 9/20/04Mech.Tech.[2]148150
150
Disconnect Seismic Anchors
0.5 daysMon 9/20/04Tue 9/21/04Mech.Tech.[2]149151SS
151
Lower Detector to Rails
0.5 daysMon 9/20/04Tue 9/21/04Mech.Tech.[2]150SS152
152
Roll Detector into WAH
1.5 daysTue 9/21/04Wed 9/22/04Mech.Tech.[2]151153,154
153
Connect Magnet LCW
1 dayWed 9/22/04Thu 9/23/04Mech.Tech.[2]152 
154
Raise/Level Detector @ IR
0.5 daysWed 9/22/04Thu 9/23/04Mech.Tech.[2]152155FF,163
155
Connect Seismic Anchors
0.5 daysWed 9/22/04Thu 9/23/04Mech.Tech.[2]154FF159,156
156
Install Buss Bridge
0.5 daysThu 9/23/04Thu 9/23/04Mech.Tech.[2]155157,160
157
Connect Electrical Power
1 dayThu 9/23/04Fri 9/24/04Electrician[2]156158
158
Connect Magnet Power
1 dayFri 9/24/04Mon 9/27/04Elect.Tech.[2]157 
159
Connect All Subsystem Utilities
2 daysThu 9/23/04Mon 9/27/04Mech.Tech.[2]155168,166
160
Connect Platform MCWS
0.5 daysThu 9/23/04Fri 9/24/04Mech.Tech.156168,161
161
Connect South Platform Stairs
1 dayFri 9/24/04Mon 9/27/04Mech.Tech.[2]160162
162
Connect Platform Bridge
0.5 daysMon 9/27/04Mon 9/27/04Mech.Tech.[2]161167
163
Connect Vacuum Pipe & Supports
0.5 daysThu 9/23/04Thu 9/23/04Mech.Tech.[2]154164
164
Vacuum Pipe Bake-out
5 daysThu 9/23/04Thu 9/30/04Mech.Tech.[2]163165
165
Survey Beam Pipe & Magnet
4 daysThu 9/30/04Wed 10/6/04Surveyors[2]164 
166
Detector Safety Certification
2 daysMon 9/27/04Wed 9/29/04 159 
167
Install Shield Wall
3 daysMon 9/27/04Thu 9/30/04Riggers[3]162171
168
Subsystems testing in WAH
20 daysMon 9/27/04Mon 10/25/04 160,159169SS+5 days
169
Install Pole Tips
2 daysMon 10/4/04Wed 10/6/04Mech.Tech.[2]168SS+5 days170
170
Install BBC Detectors
1 dayWed 10/6/04Thu 10/7/04Mech.Tech.[2]169171
171
Shutdown Activities Complete
0 daysThu 10/7/04Thu 10/7/04 167,170 

FY06

STAR FY06 Shutdown Schedule


Project Start Date: 6/26/06
Project Finish Date: 10/27/06

 

STAR FY06 v5 Shutdown

IDWBS
Name
DurationStart_DateFinish_DateResource_NamesPredecessorsSuccessors
11
STAR Detector FY06 Shutdown
87 days6/26/0610/27/06   
21.1
Disconnect Detector Utilities
10.75 days6/26/067/12/06   
31.1.1
Begin Shutdown Activities
0 days6/26/066/26/06  4SS,114SS
41.1.2
Purge TPC Gas
1 day6/26/066/26/06 3SS 
51.1.3
Remove West BBC Detector
0.25 days7/5/067/5/06Mech.Tech.1146,103
61.1.4
Disconnect West Pole Tip Utilities
0.5 days7/5/067/5/06Mech.Tech.[2]57
71.1.5
Retract West Pole Tip
0.5 days7/5/067/6/06Mech.Tech.[2]68FF
81.1.6
Install Scaffold
0.25 days7/6/067/6/06Carpenter[2]7FF9
91.1.7
Remove East BBC Detector
0.25 days7/6/067/6/06Mech.Tech.810,103
101.1.8
Disconnect East Pole Tip Utilities
0.25 days7/6/067/6/06Elect.Tech.[2]911
111.1.9
Retract East Pole Tip
0.5 days7/6/067/7/06Mech.Tech.[2]1012FF,15,13
121.1.10
Install Scaffold
0.25 days7/7/067/7/06Carpenter[2]11FF19
131.1.11
Disconnect Electrical Power
0.5 days7/7/067/7/06Electrician[2]1115,14,17
141.1.12
Disconnect Magnet Power
0.5 days7/7/067/10/06Elect.Tech.[2]1315
151.1.13
Remove Buss Bridge
0.25 days7/10/067/10/06Mech.Tech.[2]13,14,1116
161.1.14
Disconnect Platform MCWS
0.5 days7/10/067/10/06Mech.Tech.[2]1518
171.1.15
Disconnect Subsystems Utilities
2 days7/7/067/11/06Mech.Tech.13 
181.1.16
Remove South Platform Stairs
0.25 days7/11/067/11/06Mech.Tech.[2]1621
191.1.17
Remove pVPD Detectors
0.25 days7/7/067/7/06Mech.Tech.[2]1220
201.1.18
Disconnect RHIC Vacuum Pipe
3 days7/7/067/12/06Mech.Tech.[2]1924
211.1.19
Remove Seismic Anchors
0.25 days7/11/067/11/06Mech.Tech.[2]1822
221.1.20
Disconnect Magnet Water
0.25 days7/11/067/11/06Mech.Tech.[2]2123
231.1.21
Blow-out Magnet Coils
1 day7/11/067/12/06Mech.Tech.[2]2224
241.1.22
Detector Utilities Disconnected
0 days7/12/067/12/06 23,2026,57
251.2
Hydraulic System Testing
6.5 days7/12/067/21/06   
261.2.1
Run & Test Hydraulics
5 days7/12/067/19/06Mech.Tech.2427FF
271.2.2
Position Detector on Beamline
0.5 days7/19/067/19/06Mech.Tech.26FF28SS
281.2.3
Survey Detector on Beamline
2 days7/19/067/21/06Surveyors[2]27SS29
291.2.4
Hydraulics Tests Complete
0 days7/21/067/21/06 2831,67,132,85
301.3
Remove Hilman Rollers
5 days7/31/068/4/06   
311.3.1
Remove Roller Assemblies
5 days7/31/068/4/06Mech.Tech.[2]29,12332FF
321.3.2
Remove Roller Assemblies
2 days8/3/068/4/06Riggers[3]31FF33FF
331.3.3
Crate & Ship Roller Assemblies
1 day8/4/068/4/06Riggers[2],Carpenter[2]32FF34FF
341.3.4
Roller Assembly Removal Complete
0 days8/4/068/4/06 33FF 
351.4
Remove West FPD++ Detector
23.5 days7/5/068/7/06   
361.4.1
Disconnect Cabling
5 days7/5/067/11/06Mech.Tech.11437SS
371.4.2
Remove Existing Cells
13 days7/5/067/21/06Mech.Tech.36SS38
381.4.3
Remove Cabling
5 days7/31/068/4/06Mech.Tech.37,12339
391.4.4
Remove Enclosures & Shield Block
0.5 days8/7/068/7/06Riggers[3]38125,40
401.4.5
FPD++ Removal Complete
0 days8/7/068/7/06 3995
411.5
East FTPC Maintenance
15 days8/7/068/25/06   
421.5.1
Remove East IFC Air Manifolds
0.5 days8/7/068/7/06Mech.Tech.67,12343
431.5.2
Remove East Scaffold
0.5 days8/7/068/7/06Carpenter[2]4244
441.5.3
Rig East FTPC Platform
0.5 days8/8/068/8/06Riggers[3]4345SS
451.5.4
Install East FTPC Platform
0.5 days8/8/068/8/06Carpenter[2]44SS46
461.5.5
Install East FTPC Rails
0.5 days8/8/068/8/06Mech.Tech.[2]4547
471.5.6
Remove East FTPC
1 day8/9/068/9/06Mech.Tech.[2]4648,74
481.5.7
Replace East FTPC FEE
5 days8/10/068/16/06Electronic Tech4749
491.5.8
Install FTPC on Rails & Test
5 days8/17/068/23/06 4850FF
501.5.9
Install East FTPC
0.5 days8/24/068/24/06Mech.Tech.[2]49FF,7551
511.5.10
Remove East FTPC Rails
0.5 days8/24/068/24/06Mech.Tech.[2]5052
521.5.11
Rig East FTPC Platform
0.5 days8/25/068/25/06Riggers[3]5153SS
531.5.12
Remove East FTPC Platform
0.5 days8/25/068/25/06Carpenter[2]52SS54
541.5.13
Install East Scaffold
0.5 days8/25/068/25/06Carpenter[2]5355
551.5.14
FTPC Maintenance Complete
0 days8/25/068/25/06 5486,70
561.6
SSD Maintenance
27.25 days7/12/068/18/06   
571.6.1
Compressor Maintenance
5 days7/12/067/19/06 24 
581.6.2
RDO maintenance
5 days7/31/068/4/06Carpenter[2]67SS59
591.6.3
Crate Maintenance
10 days8/7/068/18/06Riggers[3]58,12360
601.6.4
SSD Maintenance Complete
0 days8/18/068/18/06 59 
611.7
BEMC Maintenance
40 days7/31/069/25/06   
621.7.1
Remove & Repair Crates
20 days7/31/068/25/06Electronic Tech12363
631.7.2
Install PMT Box Remote Power
20 days8/28/069/25/06Electronic Tech[2]6264FF
641.7.3
PMT Box Maintenance
20 days8/28/069/25/06Elect.Tech.63FF65
651.7.4
BEMC Maintenance Complete
0 days9/25/069/25/06 64145
661.8
SVT RDO Box Relocation
39 days7/31/069/22/06   
671.8.1
Remove RDO Boxes
5 days7/31/068/4/06Electronic Tech29,12368,42,58SS
681.8.2
Repair RDO Boxes
20 days8/7/069/1/06Electronic Tech6769
691.8.3
Install West RDO Boxes
2 days9/12/069/13/06Electronic Tech68,8772,81,70
701.8.4
Install Remote East RDO Boxes
5 days9/14/069/20/06Mech.Tech.69,5571
711.8.5
Rout East RDO Cables
2 days9/21/069/22/06Electronic Tech[2]7072
721.8.6
SVT RDO Box Relocation Complete
0 days9/22/069/22/06 71,69139,145
731.9
HFT Prototype Installation
10 days8/10/068/23/06   
741.9.1
Install East HFT Prototype
10 days8/10/068/23/06Mech.Tech.[2]4775
751.9.2
HFT Prototype Installed
0 days8/23/068/23/06 7450
761.10
PMD Maintenance
40 days7/31/069/25/06   
771.10.1
Replace Supermodules
30 days7/31/069/11/06 12378
781.10.2
Detector Maintenance
10 days9/12/069/25/06 7779
791.10.3
PMD Maintenance Complete
0 days9/25/069/25/06 78145
801.11
EEMC Maintenance
15 days9/14/0610/4/06   
811.11.1
PMT/MAPMT Box Maintenance
12 days9/14/069/29/06Mech.Tech.[2]69,11282SS
821.11.2
Subsystem Testing
15 days9/14/0610/4/06 81SS83
831.11.3
EEMC Maintenance Complete
0 days10/4/0610/4/06 82145,115
841.12
TPC Maintenance
35.75 days7/21/069/11/06   
851.12.1
Remove East/West Bad FEE/RDO
5 days7/21/067/28/06Electronic Tech[2]2988
861.12.2
Install East FEE/RDO
5 days8/28/069/1/06Electronic Tech[2]5589,87
871.12.3
Install West FEE/RDO
5 days9/5/069/11/06Electronic Tech[2]8689,69
881.12.4
Maintenance on Gas Room UPS
1 day7/28/067/31/06 8589
891.12.5
TPC Maintenance Complete
0 days9/11/069/11/06 88,87,86139,145,107
901.13
TOF Maintenance
5 days10/5/0610/11/06   
911.13.1
Remove Old Tray
2 days10/5/0610/6/06Mech.Tech. 92
921.13.2
Install New Trays
3 days10/9/0610/11/06Mech.Tech.9193
931.13.3
TOF Installation Complete
0 days10/11/0610/11/06 92115
941.14
FMS Installation
43 days8/7/0610/6/06   
951.14.1
Install FMS Carriages
5 days8/7/068/14/06Mech.Tech.[2]4096
961.14.2
Install FMS Cells
30 days8/14/069/26/06Mech.Tech.[2]9598FF,97SS
971.14.3
Install AC Power
5 days8/14/068/21/06Electrician[2]96SS100
981.14.4
Install FMS Enclosures
5 days9/19/069/26/06Mech.Tech.[2]96FF99
991.14.5
Install FMS Cabling
8 days9/26/0610/6/06Mech.Tech.[2]98101
1001.14.6
Install Electronics Racks
10 days8/21/069/5/06Electronic Tech[2]97101
1011.14.7
FMS Installation Complete
0 days10/6/0610/6/06 99,100145
1021.15
BBC Maintenance
25 days7/6/068/10/06   
1031.15.1
Subsystem Maintenance
20 days7/6/068/3/06 5,9104
1041.15.2
Detector Commisioning
5 days8/3/068/10/06 103105
1051.15.3
BBC Maintenance Complete
0 days8/10/068/10/06 104 
1061.16
Trigger Maintenance
10 days9/12/069/25/06   
1071.16.1
Trigger Maintenance
10 days9/12/069/25/06 89108
1081.16.2
Trigger Maintenance Complete
0 days9/25/069/25/06 107145
1091.17
Pole Tip Hose Replacement
5 days7/31/068/4/06   
1101.17.1
Remove Old Hose
2 days7/31/068/1/06Mech.Tech.[2]123111
1111.17.2
Install New Braided Hose
3 days8/2/068/4/06Mech.Tech.[2]110112
1121.17.3
Hose Replacement Complete
0 days8/4/068/4/06 11181
1131.18
Magnet Power Supply Maintenance & Test
87 days6/26/0610/27/06   
1141.18.1
Power Supply Maintenance & Test
5 days6/26/066/30/06Electronic Tech[2]3SS5,36
1151.18.2
Remove East/West Scaffold
0.5 days10/12/0610/12/06Carpenter[2]83,93116SS
1161.18.3
Install East Pole Tip
1 day10/12/0610/12/06Mech.Tech.[2]115SS117
1171.18.4
Install West Pole Tip
1 day10/13/0610/13/06Mech.Tech.[2]116118,143FF
1181.18.5
Power Supply Maintenance & Test
10 days10/16/0610/27/06Electronic Tech[2]117119
1191.18.6
Power Supply Maintenance Complete
0 days10/27/0610/27/06 118146
1201.19
C-AD Maintenance
49 days7/24/069/29/06   
1211.19.1
SGIS Modifications
10 days9/18/069/29/06Elect.Tech.[2] 130,144
1221.19.2
PS Sound Barrier Wall
10 days7/31/068/11/06 123 
1231.19.3
AC Substation Maintenance
5 days7/24/067/28/06  62,110,124,128,77,42,59,31,67,38,132,122
1241.19.4
Control Room Modification
10 days7/31/068/11/06 123126
1251.19.5
Install West Tunnel Shielding
5 days8/7/068/14/06Riggers[3]39 
1261.19.6
DAQ Room A/C Upgrade
10 days8/14/068/25/06 124127
1271.19.7
Fire Sprinkler Preaction Upgrade
10 days8/28/069/11/06 126130
1281.19.8
MCW Flow Balance
10 days7/31/068/11/06Mech.Tech.[2]123129
1291.19.9
Seal Tower Basin
5 days8/14/068/18/06Mech.Tech.[2]128 
1301.19.10
C-A Maintenance Complete
0 days9/29/069/29/06 127,121 
1311.20
Connect Detector Utilities
64 days7/31/0610/27/06   
1321.20.1
Connect Magnet LCW
1 day7/31/067/31/06Mech.Tech.[2]29,123133
1331.20.2
Install Buss Bridge
0.5 days8/1/068/1/06Mech.Tech.[2]132134,137
1341.20.3
Connect Electrical Power
1 day8/1/068/2/06Electrician[2]133135,136
1351.20.4
Connect Magnet Power
1 day8/2/068/3/06Elect.Tech.[2]134 
1361.20.5
Connect All Subsystem Utilities
1 day8/2/068/3/06Mech.Tech.[2]134 
1371.20.6
Connect Platform MCWS
0.5 days8/1/068/1/06Mech.Tech.133138
1381.20.7
Connect South Platform Stairs
1 day8/2/068/2/06Mech.Tech.[2]137 
1391.20.8
Connect Vacuum Pipe & Supports
3 days9/25/069/27/06Mech.Tech.[2]72,89140SS
1401.20.9
Vacuum Pipe Bake-out
10 days9/25/0610/6/06Mech.Tech.[2]139SS141
1411.20.10
Install START Detectors
0.5 days10/9/0610/9/06Mech.Tech.140142
1421.20.11
Survey Beam Pipe
2 days10/9/0610/11/06Surveyors[2]141143
1431.20.12
Install BBC Detectors
1 day10/13/0610/13/06Mech.Tech.[2]142,117FF 
1441.20.13
Detector Safety Certification
5 days10/2/0610/6/06 121145
1451.20.14
Subsystems testing in WAH
5 days10/9/0610/13/06 144,65,108,101,72,79,83,89146
1461.20.15
Shutdown Activities Complete
0 days10/27/0610/27/06 145,119