In Room 1-232 (the "Electronics Lab"), our goal is to remove experimental test equipment and unsupported (or poorly supported) computer systems from the "public" network. These are likely sources of Cyber Security concerns and may benefit from a less volatile network environment than the campus network. To do this, we will create a private network in the Electronics Lab, with one maintained Linux node that will be dual-homed on the public network to act as a gateway to access the private network as needed. With the introduction of one (or more) Linux box(es), eventually we hope to retire the old Sun workstation completely.
The address space we will use is 192.168.140.0/255.255.255.0 (256 IP addresses). This is "registered" with ITD network operations as a STAR private network, so that if anything "escapes" from the private space into the campus network, they will know who to call.
Given the short list of anticipated devices (below), no name server is planned, nor other common network services such as DHCP (subject to change as needed).
A Linux box named presley.star.bnl.gov is configured on the public network, with a second NIC using 192.168.140.1 to act as a manual gateway node as needed. It is in the south-west corner of the lab. An account named daqlab has been created (contact Wayne or Danny for the password if appropriate)
For the effort to replace svtbmonitor, the home directory of svtbmonitor's testlab account have been copied over to presley in /home/svtbmonitor/testlab.
Danny and Phil identified a handful of files from svtbmonitor as important so far:
The original versions of these files are all in their original (relative) paths, and modified versions for presley and the current networking setup were created and put in /home/daqlab/. The Tcl scripts were modified to account for the slightly different environment on presley and were demonstrated to work (at least the basics - still needs testing to confirm full functionality). The "grab" executable had to be recompiled from source (simple enough - the required source code consists of "grab.c" and only required a single minor change for the new environment on presley). So far so good there.
Two small "desktop" 10/100 Mbps switches have been connected to each other to serve as the "backbone":
This is easy to expand with one or two 16-port switches if needed (well, it actually is needed as I write this...). (In fact, these switches have been rather fluid in the first months, coming and going and being swapped for others, all at a slight inconvenience to those of us trying to work with them...)
[Feb. 19, 2009 update -- the physical layout of switches and cables has been switched around many times since this description and I don't know the current state.]
The old networking (not to mention the serial lines) is a mess of cables, old hubs and switches that I plan to ignore as long as possible, though most should be removed if it isn't nailed down. [Feb. 19, 2009 - some clean up appears to have been done by the folks working in the lab.]
Towards this end we've identified the following remaining tasks:
Configure backups of the home directories on presley as another safety net for the critical content from svtbmonitor that has been transferred over.
Jack Engelage and Hank Crawford have transferred a bunch of files from svtbmonitor to presley [are they done?]. A "trigger" group was created containing Jack, Chris and Hank. They have /home/trigger to share amongst themselves.
The biggies:
VxWorks compilers for Linux and booting the VME processors from presley. [Feb 19, 2009 update: Yury Gorbunov (and Jack Engelage?) have made successful boots of trgfe3 from presley via FTP, so it looks like svtbmonitor has a chance of being retired at some point. Sample boot parameters are attached]
This is my first test page.
ID | Name | Duration | Start_Date | Finish_Date | Resource_Names | Predecessors | Successors |
---|---|---|---|---|---|---|---|
1 | STAR Detector Operations | 211.35 days | Mon 1/5/04 | Mon 10/25/04 | |||
2 | Physics Run FY04 | 96 days | Mon 1/5/04 | Sat 5/15/04 | 5FF | ||
3 | Start Shutdown Activities | 116.35 days | Sat 5/15/04 | Mon 10/25/04 | |||
4 | Move Detector into AB | 14.6 days | Sat 5/15/04 | Thu 6/3/04 | |||
5 | Purge TPC Gas | 1 day | Sat 5/15/04 | Sat 5/15/04 | 2FF | 6SS | |
6 | Subsystem Testing | 6 days | Sat 5/15/04 | Fri 5/21/04 | 5SS | 7 | |
7 | Retract PMD Detector | 0.1 days | Mon 5/24/04 | Mon 5/24/04 | Mech.Tech. | 6 | 8 |
8 | Remove East BBC Detector | 0.25 days | Mon 5/24/04 | Mon 5/24/04 | Mech.Tech. | 7 | 9 |
9 | Retract East Pole Tip | 0.5 days | Mon 5/24/04 | Mon 5/24/04 | Mech.Tech.[2] | 8 | 10FF |
10 | Install Scaffold | 0.25 days | Mon 5/24/04 | Mon 5/24/04 | Carpenter[2] | 9FF | 12,11 |
11 | Remove Shield Wall | 2.5 days | Mon 5/24/04 | Thu 5/27/04 | Riggers[3] | 10 | 26,23,16SS,18,135 |
12 | Remove West Pole Tip Utilities | 0.25 days | Mon 5/24/04 | Tue 5/25/04 | Mech.Tech. | 10 | 13 |
13 | Remove West BBC Detector | 0.25 days | Tue 5/25/04 | Tue 5/25/04 | Mech.Tech. | 12 | 14 |
14 | Retract West Pole Tip | 0.5 days | Tue 5/25/04 | Tue 5/25/04 | Mech.Tech.[2] | 13 | 15FF |
15 | Install Scaffold | 0.13 days | Tue 5/25/04 | Tue 5/25/04 | Carpenter[2] | 14FF | |
16 | Disconnect Electrical Power | 0.5 days | Mon 5/24/04 | Tue 5/25/04 | Electrician[2] | 11SS | 18,17 |
17 | Disconnect Magnet Power | 0.5 days | Tue 5/25/04 | Tue 5/25/04 | Elect.Tech.[2] | 16 | 18 |
18 | Remove Buss Bridge | 0.25 days | Thu 5/27/04 | Thu 5/27/04 | Mech.Tech.[2] | 16,17,11 | 19,21 |
19 | Disconnect Platform MCWS | 0.5 days | Thu 5/27/04 | Fri 5/28/04 | Mech.Tech. | 18 | 20 |
20 | Disconnect Subsystems Utilities | 1 day | Fri 5/28/04 | Mon 5/31/04 | Mech.Tech. | 19 | 26 |
21 | Remove Platform Bridge | 0.25 days | Thu 5/27/04 | Thu 5/27/04 | Mech.Tech.[2] | 18 | 26,22 |
22 | Remove South Platform Stairs | 0.25 days | Thu 5/27/04 | Fri 5/28/04 | Mech.Tech.[2] | 21 | 26,24 |
23 | Disconnect RHIC Vacuum Pipe | 0.5 days | Thu 5/27/04 | Thu 5/27/04 | Mech.Tech. | 11 | |
24 | Remove Seismic Anchors | 0.25 days | Fri 5/28/04 | Fri 5/28/04 | Mech.Tech.[2] | 22 | 25 |
25 | Disconnect Magnet LCW | 0.25 days | Fri 5/28/04 | Fri 5/28/04 | Mech.Tech.[2] | 24 | 26 |
26 | Roll Detector into AB | 1 day | Mon 5/31/04 | Tue 6/1/04 | Mech.Tech.[2] | 11,21,22,25,20 | 27 |
27 | Blow-out Magnet Coils | 0.5 days | Tue 6/1/04 | Tue 6/1/04 | Mech.Tech.[2] | 26 | 28 |
28 | Connect South Platform Stairs | 0.5 days | Tue 6/1/04 | Wed 6/2/04 | Mech.Tech.[2] | 27 | 29 |
29 | Connect Platform Bridge | 0.5 days | Wed 6/2/04 | Wed 6/2/04 | Mech.Tech.[2] | 28 | 31,30 |
30 | Connect Seismic Anchors | 0.5 days | Wed 6/2/04 | Thu 6/3/04 | Mech.Tech. | 29 | |
31 | Install Buss Bridge | 0.5 days | Wed 6/2/04 | Thu 6/3/04 | Mech.Tech.[2] | 29 | 32 |
32 | Connect Electrical Power | 0.5 days | Thu 6/3/04 | Thu 6/3/04 | Electrician[2] | 31 | 33SS |
33 | Connect Subsystems Utilities | 0.5 days | Thu 6/3/04 | Thu 6/3/04 | Mech.Tech. | 32SS | 34SS |
34 | Connect Platform MCWS | 0.5 days | Thu 6/3/04 | Thu 6/3/04 | Mech.Tech. | 33SS | 35 |
35 | Detector In AB | 0 days | Thu 6/3/04 | Thu 6/3/04 | 34 | 37,117,121 | |
36 | Remove East & West FTPC | 13.75 days | Thu 6/3/04 | Wed 6/23/04 | |||
37 | Remove E/W IFC Air Manifolds | 0.25 days | Thu 6/3/04 | Thu 6/3/04 | Mech.Tech. | 35 | 38 |
38 | Remove East & West Scaffold | 0.5 days | Thu 6/3/04 | Fri 6/4/04 | Carpenter[2] | 37 | 39 |
39 | Install West Platform & Rails | 1 day | Fri 6/4/04 | Mon 6/7/04 | Carpenter[2] | 38 | 40,41 |
40 | Remove West FTPC | 0.5 days | Mon 6/7/04 | Mon 6/7/04 | Mech.Tech. | 39 | 45 |
41 | Rig Installation Frame into AB | 0.5 days | Mon 6/7/04 | Mon 6/7/04 | Riggers[3] | 39 | 42SS |
42 | Install East Installation Frame | 0.5 days | Mon 6/7/04 | Mon 6/7/04 | Mech.Tech.[2] | 41SS | 43 |
43 | Install East Rails | 1 day | Mon 6/7/04 | Tue 6/8/04 | Mech.Tech.[2] | 42 | 44 |
44 | Remove East FTPC | 0.5 days | Tue 6/8/04 | Wed 6/9/04 | Mech.Tech.[2] | 43 | 45 |
45 | East & West FTPC's Removed | 0 days | Wed 6/9/04 | Wed 6/9/04 | 40,44 | 46,48 | |
46 | Maintenance on FTPC's | 10 days | Wed 6/9/04 | Wed 6/23/04 | Electronic Tech | 45 | |
47 | Remove Cone | 11.5 days | Wed 6/9/04 | Thu 6/24/04 | |||
48 | Disconnect Utilities | 4 days | Wed 6/9/04 | Tue 6/15/04 | Mech.Tech. | 45 | 49 |
49 | Remove Cone from IFC | 0.5 days | Tue 6/15/04 | Tue 6/15/04 | Mech.Tech. | 48 | 76,126 |
50 | Remove East Installation Frame | 1 day | Tue 6/22/04 | Wed 6/23/04 | Mech.Tech.[2] | 76,126 | 51FF |
51 | Remove Installation Frame from AB | 0.5 days | Wed 6/23/04 | Wed 6/23/04 | Riggers[3] | 50FF | 52 |
52 | Remove Installation Frame West | 1 day | Wed 6/23/04 | Thu 6/24/04 | Carpenter[2] | 51 | 53 |
53 | Cone Removed | 0 days | Thu 6/24/04 | Thu 6/24/04 | 52 | 57 | |
54 | Install East BEMC Modules | 47.5 days | Mon 6/14/04 | Wed 8/18/04 | |||
55 | (30) Modules Delivered | 4 days | Mon 6/14/04 | Fri 6/18/04 | Riggers[3] | 57FF-5 days | 56FF |
56 | (30) Modules Staged in AB | 4 days | Mon 6/14/04 | Fri 6/18/04 | Mech.Tech.[2] | 55FF | |
57 | Install East & West Scaffold | 0.5 days | Thu 6/24/04 | Fri 6/25/04 | Carpenter[2] | 53 | 58,55FF-5 days |
58 | Remove East Side Cables & Tray | 3 days | Fri 6/25/04 | Wed 6/30/04 | Mech.Tech.[2] | 57 | 59 |
59 | Erect Installation Fixture S.E. Upper | 0.5 days | Wed 6/30/04 | Wed 6/30/04 | Mech.Tech.[2] | 58 | 60 |
60 | Remove S.E. TPC Support Arm | 0.25 days | Wed 6/30/04 | Thu 7/1/04 | Mech.Tech.[2] | 59 | 61 |
61 | Install Modules 106-103 | 4 days | Thu 7/1/04 | Wed 7/7/04 | Mech.Tech.[2] | 60 | 62 |
62 | Erect Installation Fixture S.E. Lower | 0.5 days | Wed 7/7/04 | Wed 7/7/04 | Mech.Tech.[2] | 61 | 63 |
63 | Install Modules 102-89 | 14 days | Wed 7/7/04 | Tue 7/27/04 | Mech.Tech.[2] | 62 | 64 |
64 | Install S.E. TPC Support Arm | 0.5 days | Tue 7/27/04 | Wed 7/28/04 | Mech.Tech.[2] | 63 | 65 |
65 | Erect Installation Fixture N.E. Lower | 0.5 days | Wed 7/28/04 | Wed 7/28/04 | Mech.Tech.[2] | 64 | 66 |
66 | Install Modules 77-88 | 12 days | Wed 7/28/04 | Fri 8/13/04 | Mech.Tech.[2] | 65 | 67 |
67 | Remove Installation Fixture | 0.25 days | Fri 8/13/04 | Fri 8/13/04 | Mech.Tech.[2] | 66 | 68 |
68 | Install East Side Cables & Tray | 3 days | Fri 8/13/04 | Wed 8/18/04 | Mech.Tech.[2] | 67 | 69 |
69 | East BEMC Installation Complete | 0 days | Wed 8/18/04 | Wed 8/18/04 | 68 | 82,72 | |
70 | Install BEMC PMT Boxes | 35 days | Wed 7/14/04 | Wed 9/1/04 | |||
71 | Install 208 VAC Power | 15 days | Wed 7/14/04 | Wed 8/4/04 | Electrician[2] | 72SF-10 days | |
72 | Install PMT Boxes | 10 days | Wed 8/18/04 | Wed 9/1/04 | Mech.Tech.[2] | 69 | 73FF,71SF-10 days |
73 | Install Electronics | 20 days | Wed 8/4/04 | Wed 9/1/04 | Electronic Tech | 72FF | 74 |
74 | PMT Box Installation Complete | 0 days | Wed 9/1/04 | Wed 9/1/04 | 73 | 144 | |
75 | Install SSD | 20.5 days | Tue 6/15/04 | Wed 7/14/04 | |||
76 | Rig Cone to Cleanroom Roof | 0.5 days | Tue 6/15/04 | Wed 6/16/04 | Mech.Tech. | 49 | 77,50 |
77 | Install SSD on Cone | 20 days | Wed 6/16/04 | Wed 7/14/04 | Mech.Tech. | 76 | 78SS,80 |
78 | Install LV Crate & Cables | 5 days | Wed 6/16/04 | Wed 6/23/04 | Electronic Tech | 77SS | 79 |
79 | Install RDO Boxes | 5 days | Wed 6/23/04 | Wed 6/30/04 | Electronic Tech | 78 | |
80 | SSD Installed on Cone | 0 days | Wed 7/14/04 | Wed 7/14/04 | 77 | 85 | |
81 | Install Cone | 20.5 days | Wed 8/18/04 | Thu 9/16/04 | |||
82 | Rig Installation Frame into AB | 0.5 days | Wed 8/18/04 | Thu 8/19/04 | Riggers[3] | 69 | 83SS |
83 | Install East Installation Frame | 0.5 days | Wed 8/18/04 | Thu 8/19/04 | Mech.Tech.[2] | 82SS | 84 |
84 | Install Tables & Rails | 0.5 days | Thu 8/19/04 | Thu 8/19/04 | Mech.Tech. | 83 | 85 |
85 | Rig Cone to Rails | 0.5 days | Thu 8/19/04 | Fri 8/20/04 | Mech.Tech.[2] | 84,80 | 86 |
86 | Survey SSD to SVT | 2 days | Fri 8/20/04 | Tue 8/24/04 | Surveyors[2] | 85 | 87 |
87 | Complete SSD Installation | 2 days | Tue 8/24/04 | Thu 8/26/04 | Mech.Tech. | 86 | 88 |
88 | Test Utility Connections | 1 day | Thu 8/26/04 | Fri 8/27/04 | Electronic Tech | 87 | 89FF |
89 | Clean TPC IFC | 1 day | Thu 8/26/04 | Fri 8/27/04 | Mech.Tech. | 88FF | 90 |
90 | Install Cone in Detector | 0.5 days | Fri 8/27/04 | Fri 8/27/04 | Mech.Tech. | 89 | 91 |
91 | Test IFC High Voltage | 0.5 days | Fri 8/27/04 | Mon 8/30/04 | Electronic Tech | 90 | 92 |
92 | Survey TPC to Magnet | 2 days | Mon 8/30/04 | Wed 9/1/04 | Surveyors[2] | 91 | 93 |
93 | Survey SVT to TPC | 2 days | Wed 9/1/04 | Fri 9/3/04 | Surveyors[2] | 92 | 94 |
94 | Install East Partitions | 0.5 days | Fri 9/3/04 | Fri 9/3/04 | Mech.Tech. | 93 | 110 |
95 | Connect Water Lines | 0.5 days | Mon 9/6/04 | Tue 9/7/04 | Mech.Tech. | 110 | 96 |
96 | Connect RDO Cables | 1 day | Tue 9/7/04 | Wed 9/8/04 | Electronic Tech | 95 | 97 |
97 | Remove East Rails from IFC | 0.5 days | Wed 9/8/04 | Wed 9/8/04 | Mech.Tech.[2] | 96 | 98 |
98 | Remove East Installation Frame | 0.5 days | Wed 9/8/04 | Thu 9/9/04 | Mech.Tech.[2] | 97 | 99FF |
99 | Remove Installation Frame from AB | 0.25 days | Thu 9/9/04 | Thu 9/9/04 | Riggers[3] | 98FF | 100 |
100 | East Side Complete | 0 days | Thu 9/9/04 | Thu 9/9/04 | 99 | 107,101 | |
101 | Install West Partitions | 0.5 days | Thu 9/9/04 | Thu 9/9/04 | Mech.Tech. | 100 | 112 |
102 | Connect Water Lines | 0.5 days | Mon 9/13/04 | Mon 9/13/04 | Mech.Tech. | 114 | 103 |
103 | Connect RDO Cables | 1 day | Mon 9/13/04 | Tue 9/14/04 | Electronic Tech | 102 | 104 |
104 | Remove West Rails from IFC | 0.5 days | Tue 9/14/04 | Wed 9/15/04 | Mech.Tech. | 103 | 105 |
105 | Remove Installation Frame West | 1 day | Wed 9/15/04 | Thu 9/16/04 | Carpenter[2] | 104 | 106 |
106 | West Side Complete | 0 days | Thu 9/16/04 | Thu 9/16/04 | 105 | 107 | |
107 | Cone Installation Complete | 0 days | Thu 9/16/04 | Thu 9/16/04 | 100,106 | 144 | |
108 | Install FTPC East & West in AB | 12.5 days | Wed 8/25/04 | Mon 9/13/04 | |||
109 | Run & Test N. Platform | 5 days | Wed 8/25/04 | Wed 9/1/04 | Electronic Tech | 110SF-2 days | |
110 | Install East FTPC in Detector | 1 day | Fri 9/3/04 | Mon 9/6/04 | Mech.Tech.[2] | 94 | 115,109SF-2 days,95 |
111 | Run & Test N. Platform | 5 days | Wed 9/1/04 | Wed 9/8/04 | Electronic Tech | 114SF-2 days | |
112 | Remove West Scaffold | 0.25 days | Thu 9/9/04 | Fri 9/10/04 | Carpenter[2] | 101 | 113 |
113 | Install West Platform & Rails | 0.25 days | Fri 9/10/04 | Fri 9/10/04 | Carpenter[2] | 112 | 114 |
114 | Install West FTPC in Detector | 1 day | Fri 9/10/04 | Mon 9/13/04 | Mech.Tech.[2] | 113 | 115,111SF-2 days,102 |
115 | FTPC Installed in AB | 0 days | Mon 9/13/04 | Mon 9/13/04 | 114,110 | ||
116 | PMD Maintenance | 40 days | Thu 6/3/04 | Thu 7/29/04 | |||
117 | Subsystem Maintenance | 30 days | Thu 6/3/04 | Thu 7/15/04 | 35 | 118 | |
118 | Detector Commisioning | 10 days | Thu 7/15/04 | Thu 7/29/04 | 117 | 119 | |
119 | PMD Maintenance Complete | 0 days | Thu 7/29/04 | Thu 7/29/04 | 118 | ||
120 | EEMC Maintenance | 90 days | Thu 6/3/04 | Thu 10/7/04 | |||
121 | Maintenance | 50 days | Thu 6/3/04 | Thu 8/12/04 | 35 | 122SS | |
122 | MAPMT Installation | 80 days | Thu 6/3/04 | Thu 9/23/04 | Mech.Tech.[2] | 121SS | 123 |
123 | Subsystem Testing | 10 days | Thu 9/23/04 | Thu 10/7/04 | 122 | 124 | |
124 | EEMC Maintenance Complete | 0 days | Thu 10/7/04 | Thu 10/7/04 | 123 | ||
125 | TPC Maintenance | 50 days | Tue 6/15/04 | Tue 8/24/04 | |||
126 | Repair IFC Strip Short | 5 days | Tue 6/15/04 | Tue 6/22/04 | Mech.Tech. | 49 | 127,50,131SS |
127 | Modify Resistor Chain | 5 days | Tue 6/22/04 | Tue 6/29/04 | Mech.Tech. | 126 | 128 |
128 | FEE & RDO Maintenance | 40 days | Tue 6/29/04 | Tue 8/24/04 | Electronic Tech | 127 | 129 |
129 | TPC Maintenance Complete | 0 days | Tue 8/24/04 | Tue 8/24/04 | 128 | ||
130 | TOF Maintenance | 15 days | Tue 6/15/04 | Tue 7/6/04 | |||
131 | Tray Maintenance | 10 days | Tue 6/15/04 | Tue 6/29/04 | 126SS | 132 | |
132 | Detector Testing | 5 days | Tue 6/29/04 | Tue 7/6/04 | 131 | 133 | |
133 | TOFp Maintenance Complete | 0 days | Tue 7/6/04 | Tue 7/6/04 | 132 | ||
134 | FPD Installation | 20 days | Thu 5/27/04 | Thu 6/24/04 | |||
135 | Install West Detectors | 10 days | Thu 5/27/04 | Thu 6/10/04 | Mech.Tech. | 11 | 136 |
136 | Install N. E. Stand for 20-cm Travel | 5 days | Thu 6/10/04 | Thu 6/17/04 | Mech.Tech.[2] | 135 | 137 |
137 | Detector Commisioning | 5 days | Thu 6/17/04 | Thu 6/24/04 | 136 | 138 | |
138 | FPD Installation Complete | 0 days | Thu 6/24/04 | Thu 6/24/04 | 137 | 140 | |
139 | BBC Maintenance | 15 days | Thu 6/24/04 | Thu 7/15/04 | |||
140 | Subsystem Maintenance | 10 days | Thu 6/24/04 | Thu 7/8/04 | 138 | 141 | |
141 | Detector Commisioning | 5 days | Thu 7/8/04 | Thu 7/15/04 | 140 | 142 | |
142 | BBC Maintenance Complete | 0 days | Thu 7/15/04 | Thu 7/15/04 | 141 | ||
143 | Move Detector into WAH | 27 days | Thu 9/16/04 | Mon 10/25/04 | |||
144 | Disconnect Electrical Power | 0.5 days | Thu 9/16/04 | Thu 9/16/04 | Electrician[2] | 107,74 | 147,145SS,146SS |
145 | Disconnect Platform MCWS | 0.5 days | Thu 9/16/04 | Thu 9/16/04 | Mech.Tech. | 144SS | |
146 | Disconnect TPC Utilities | 0.5 days | Thu 9/16/04 | Thu 9/16/04 | Mech.Tech. | 144SS | |
147 | Remove Buss Bridge | 0.5 days | Thu 9/16/04 | Fri 9/17/04 | Mech.Tech.[2] | 144 | 148 |
148 | Remove Platform Bridge | 0.5 days | Fri 9/17/04 | Fri 9/17/04 | Mech.Tech.[2] | 147 | 149 |
149 | Remove South Platform Stairs | 1 day | Fri 9/17/04 | Mon 9/20/04 | Mech.Tech.[2] | 148 | 150 |
150 | Disconnect Seismic Anchors | 0.5 days | Mon 9/20/04 | Tue 9/21/04 | Mech.Tech.[2] | 149 | 151SS |
151 | Lower Detector to Rails | 0.5 days | Mon 9/20/04 | Tue 9/21/04 | Mech.Tech.[2] | 150SS | 152 |
152 | Roll Detector into WAH | 1.5 days | Tue 9/21/04 | Wed 9/22/04 | Mech.Tech.[2] | 151 | 153,154 |
153 | Connect Magnet LCW | 1 day | Wed 9/22/04 | Thu 9/23/04 | Mech.Tech.[2] | 152 | |
154 | Raise/Level Detector @ IR | 0.5 days | Wed 9/22/04 | Thu 9/23/04 | Mech.Tech.[2] | 152 | 155FF,163 |
155 | Connect Seismic Anchors | 0.5 days | Wed 9/22/04 | Thu 9/23/04 | Mech.Tech.[2] | 154FF | 159,156 |
156 | Install Buss Bridge | 0.5 days | Thu 9/23/04 | Thu 9/23/04 | Mech.Tech.[2] | 155 | 157,160 |
157 | Connect Electrical Power | 1 day | Thu 9/23/04 | Fri 9/24/04 | Electrician[2] | 156 | 158 |
158 | Connect Magnet Power | 1 day | Fri 9/24/04 | Mon 9/27/04 | Elect.Tech.[2] | 157 | |
159 | Connect All Subsystem Utilities | 2 days | Thu 9/23/04 | Mon 9/27/04 | Mech.Tech.[2] | 155 | 168,166 |
160 | Connect Platform MCWS | 0.5 days | Thu 9/23/04 | Fri 9/24/04 | Mech.Tech. | 156 | 168,161 |
161 | Connect South Platform Stairs | 1 day | Fri 9/24/04 | Mon 9/27/04 | Mech.Tech.[2] | 160 | 162 |
162 | Connect Platform Bridge | 0.5 days | Mon 9/27/04 | Mon 9/27/04 | Mech.Tech.[2] | 161 | 167 |
163 | Connect Vacuum Pipe & Supports | 0.5 days | Thu 9/23/04 | Thu 9/23/04 | Mech.Tech.[2] | 154 | 164 |
164 | Vacuum Pipe Bake-out | 5 days | Thu 9/23/04 | Thu 9/30/04 | Mech.Tech.[2] | 163 | 165 |
165 | Survey Beam Pipe & Magnet | 4 days | Thu 9/30/04 | Wed 10/6/04 | Surveyors[2] | 164 | |
166 | Detector Safety Certification | 2 days | Mon 9/27/04 | Wed 9/29/04 | 159 | ||
167 | Install Shield Wall | 3 days | Mon 9/27/04 | Thu 9/30/04 | Riggers[3] | 162 | 171 |
168 | Subsystems testing in WAH | 20 days | Mon 9/27/04 | Mon 10/25/04 | 160,159 | 169SS+5 days | |
169 | Install Pole Tips | 2 days | Mon 10/4/04 | Wed 10/6/04 | Mech.Tech.[2] | 168SS+5 days | 170 |
170 | Install BBC Detectors | 1 day | Wed 10/6/04 | Thu 10/7/04 | Mech.Tech.[2] | 169 | 171 |
171 | Shutdown Activities Complete | 0 days | Thu 10/7/04 | Thu 10/7/04 | 167,170 |
Project Start Date: 6/26/06
Project Finish Date: 10/27/06
ID | WBS | Name | Duration | Start_Date | Finish_Date | Resource_Names | Predecessors | Successors |
---|---|---|---|---|---|---|---|---|
1 | 1 | STAR Detector FY06 Shutdown | 87 days | 6/26/06 | 10/27/06 | |||
2 | 1.1 | Disconnect Detector Utilities | 10.75 days | 6/26/06 | 7/12/06 | |||
3 | 1.1.1 | Begin Shutdown Activities | 0 days | 6/26/06 | 6/26/06 | 4SS,114SS | ||
4 | 1.1.2 | Purge TPC Gas | 1 day | 6/26/06 | 6/26/06 | 3SS | ||
5 | 1.1.3 | Remove West BBC Detector | 0.25 days | 7/5/06 | 7/5/06 | Mech.Tech. | 114 | 6,103 |
6 | 1.1.4 | Disconnect West Pole Tip Utilities | 0.5 days | 7/5/06 | 7/5/06 | Mech.Tech.[2] | 5 | 7 |
7 | 1.1.5 | Retract West Pole Tip | 0.5 days | 7/5/06 | 7/6/06 | Mech.Tech.[2] | 6 | 8FF |
8 | 1.1.6 | Install Scaffold | 0.25 days | 7/6/06 | 7/6/06 | Carpenter[2] | 7FF | 9 |
9 | 1.1.7 | Remove East BBC Detector | 0.25 days | 7/6/06 | 7/6/06 | Mech.Tech. | 8 | 10,103 |
10 | 1.1.8 | Disconnect East Pole Tip Utilities | 0.25 days | 7/6/06 | 7/6/06 | Elect.Tech.[2] | 9 | 11 |
11 | 1.1.9 | Retract East Pole Tip | 0.5 days | 7/6/06 | 7/7/06 | Mech.Tech.[2] | 10 | 12FF,15,13 |
12 | 1.1.10 | Install Scaffold | 0.25 days | 7/7/06 | 7/7/06 | Carpenter[2] | 11FF | 19 |
13 | 1.1.11 | Disconnect Electrical Power | 0.5 days | 7/7/06 | 7/7/06 | Electrician[2] | 11 | 15,14,17 |
14 | 1.1.12 | Disconnect Magnet Power | 0.5 days | 7/7/06 | 7/10/06 | Elect.Tech.[2] | 13 | 15 |
15 | 1.1.13 | Remove Buss Bridge | 0.25 days | 7/10/06 | 7/10/06 | Mech.Tech.[2] | 13,14,11 | 16 |
16 | 1.1.14 | Disconnect Platform MCWS | 0.5 days | 7/10/06 | 7/10/06 | Mech.Tech.[2] | 15 | 18 |
17 | 1.1.15 | Disconnect Subsystems Utilities | 2 days | 7/7/06 | 7/11/06 | Mech.Tech. | 13 | |
18 | 1.1.16 | Remove South Platform Stairs | 0.25 days | 7/11/06 | 7/11/06 | Mech.Tech.[2] | 16 | 21 |
19 | 1.1.17 | Remove pVPD Detectors | 0.25 days | 7/7/06 | 7/7/06 | Mech.Tech.[2] | 12 | 20 |
20 | 1.1.18 | Disconnect RHIC Vacuum Pipe | 3 days | 7/7/06 | 7/12/06 | Mech.Tech.[2] | 19 | 24 |
21 | 1.1.19 | Remove Seismic Anchors | 0.25 days | 7/11/06 | 7/11/06 | Mech.Tech.[2] | 18 | 22 |
22 | 1.1.20 | Disconnect Magnet Water | 0.25 days | 7/11/06 | 7/11/06 | Mech.Tech.[2] | 21 | 23 |
23 | 1.1.21 | Blow-out Magnet Coils | 1 day | 7/11/06 | 7/12/06 | Mech.Tech.[2] | 22 | 24 |
24 | 1.1.22 | Detector Utilities Disconnected | 0 days | 7/12/06 | 7/12/06 | 23,20 | 26,57 | |
25 | 1.2 | Hydraulic System Testing | 6.5 days | 7/12/06 | 7/21/06 | |||
26 | 1.2.1 | Run & Test Hydraulics | 5 days | 7/12/06 | 7/19/06 | Mech.Tech. | 24 | 27FF |
27 | 1.2.2 | Position Detector on Beamline | 0.5 days | 7/19/06 | 7/19/06 | Mech.Tech. | 26FF | 28SS |
28 | 1.2.3 | Survey Detector on Beamline | 2 days | 7/19/06 | 7/21/06 | Surveyors[2] | 27SS | 29 |
29 | 1.2.4 | Hydraulics Tests Complete | 0 days | 7/21/06 | 7/21/06 | 28 | 31,67,132,85 | |
30 | 1.3 | Remove Hilman Rollers | 5 days | 7/31/06 | 8/4/06 | |||
31 | 1.3.1 | Remove Roller Assemblies | 5 days | 7/31/06 | 8/4/06 | Mech.Tech.[2] | 29,123 | 32FF |
32 | 1.3.2 | Remove Roller Assemblies | 2 days | 8/3/06 | 8/4/06 | Riggers[3] | 31FF | 33FF |
33 | 1.3.3 | Crate & Ship Roller Assemblies | 1 day | 8/4/06 | 8/4/06 | Riggers[2],Carpenter[2] | 32FF | 34FF |
34 | 1.3.4 | Roller Assembly Removal Complete | 0 days | 8/4/06 | 8/4/06 | 33FF | ||
35 | 1.4 | Remove West FPD++ Detector | 23.5 days | 7/5/06 | 8/7/06 | |||
36 | 1.4.1 | Disconnect Cabling | 5 days | 7/5/06 | 7/11/06 | Mech.Tech. | 114 | 37SS |
37 | 1.4.2 | Remove Existing Cells | 13 days | 7/5/06 | 7/21/06 | Mech.Tech. | 36SS | 38 |
38 | 1.4.3 | Remove Cabling | 5 days | 7/31/06 | 8/4/06 | Mech.Tech. | 37,123 | 39 |
39 | 1.4.4 | Remove Enclosures & Shield Block | 0.5 days | 8/7/06 | 8/7/06 | Riggers[3] | 38 | 125,40 |
40 | 1.4.5 | FPD++ Removal Complete | 0 days | 8/7/06 | 8/7/06 | 39 | 95 | |
41 | 1.5 | East FTPC Maintenance | 15 days | 8/7/06 | 8/25/06 | |||
42 | 1.5.1 | Remove East IFC Air Manifolds | 0.5 days | 8/7/06 | 8/7/06 | Mech.Tech. | 67,123 | 43 |
43 | 1.5.2 | Remove East Scaffold | 0.5 days | 8/7/06 | 8/7/06 | Carpenter[2] | 42 | 44 |
44 | 1.5.3 | Rig East FTPC Platform | 0.5 days | 8/8/06 | 8/8/06 | Riggers[3] | 43 | 45SS |
45 | 1.5.4 | Install East FTPC Platform | 0.5 days | 8/8/06 | 8/8/06 | Carpenter[2] | 44SS | 46 |
46 | 1.5.5 | Install East FTPC Rails | 0.5 days | 8/8/06 | 8/8/06 | Mech.Tech.[2] | 45 | 47 |
47 | 1.5.6 | Remove East FTPC | 1 day | 8/9/06 | 8/9/06 | Mech.Tech.[2] | 46 | 48,74 |
48 | 1.5.7 | Replace East FTPC FEE | 5 days | 8/10/06 | 8/16/06 | Electronic Tech | 47 | 49 |
49 | 1.5.8 | Install FTPC on Rails & Test | 5 days | 8/17/06 | 8/23/06 | 48 | 50FF | |
50 | 1.5.9 | Install East FTPC | 0.5 days | 8/24/06 | 8/24/06 | Mech.Tech.[2] | 49FF,75 | 51 |
51 | 1.5.10 | Remove East FTPC Rails | 0.5 days | 8/24/06 | 8/24/06 | Mech.Tech.[2] | 50 | 52 |
52 | 1.5.11 | Rig East FTPC Platform | 0.5 days | 8/25/06 | 8/25/06 | Riggers[3] | 51 | 53SS |
53 | 1.5.12 | Remove East FTPC Platform | 0.5 days | 8/25/06 | 8/25/06 | Carpenter[2] | 52SS | 54 |
54 | 1.5.13 | Install East Scaffold | 0.5 days | 8/25/06 | 8/25/06 | Carpenter[2] | 53 | 55 |
55 | 1.5.14 | FTPC Maintenance Complete | 0 days | 8/25/06 | 8/25/06 | 54 | 86,70 | |
56 | 1.6 | SSD Maintenance | 27.25 days | 7/12/06 | 8/18/06 | |||
57 | 1.6.1 | Compressor Maintenance | 5 days | 7/12/06 | 7/19/06 | 24 | ||
58 | 1.6.2 | RDO maintenance | 5 days | 7/31/06 | 8/4/06 | Carpenter[2] | 67SS | 59 |
59 | 1.6.3 | Crate Maintenance | 10 days | 8/7/06 | 8/18/06 | Riggers[3] | 58,123 | 60 |
60 | 1.6.4 | SSD Maintenance Complete | 0 days | 8/18/06 | 8/18/06 | 59 | ||
61 | 1.7 | BEMC Maintenance | 40 days | 7/31/06 | 9/25/06 | |||
62 | 1.7.1 | Remove & Repair Crates | 20 days | 7/31/06 | 8/25/06 | Electronic Tech | 123 | 63 |
63 | 1.7.2 | Install PMT Box Remote Power | 20 days | 8/28/06 | 9/25/06 | Electronic Tech[2] | 62 | 64FF |
64 | 1.7.3 | PMT Box Maintenance | 20 days | 8/28/06 | 9/25/06 | Elect.Tech. | 63FF | 65 |
65 | 1.7.4 | BEMC Maintenance Complete | 0 days | 9/25/06 | 9/25/06 | 64 | 145 | |
66 | 1.8 | SVT RDO Box Relocation | 39 days | 7/31/06 | 9/22/06 | |||
67 | 1.8.1 | Remove RDO Boxes | 5 days | 7/31/06 | 8/4/06 | Electronic Tech | 29,123 | 68,42,58SS |
68 | 1.8.2 | Repair RDO Boxes | 20 days | 8/7/06 | 9/1/06 | Electronic Tech | 67 | 69 |
69 | 1.8.3 | Install West RDO Boxes | 2 days | 9/12/06 | 9/13/06 | Electronic Tech | 68,87 | 72,81,70 |
70 | 1.8.4 | Install Remote East RDO Boxes | 5 days | 9/14/06 | 9/20/06 | Mech.Tech. | 69,55 | 71 |
71 | 1.8.5 | Rout East RDO Cables | 2 days | 9/21/06 | 9/22/06 | Electronic Tech[2] | 70 | 72 |
72 | 1.8.6 | SVT RDO Box Relocation Complete | 0 days | 9/22/06 | 9/22/06 | 71,69 | 139,145 | |
73 | 1.9 | HFT Prototype Installation | 10 days | 8/10/06 | 8/23/06 | |||
74 | 1.9.1 | Install East HFT Prototype | 10 days | 8/10/06 | 8/23/06 | Mech.Tech.[2] | 47 | 75 |
75 | 1.9.2 | HFT Prototype Installed | 0 days | 8/23/06 | 8/23/06 | 74 | 50 | |
76 | 1.10 | PMD Maintenance | 40 days | 7/31/06 | 9/25/06 | |||
77 | 1.10.1 | Replace Supermodules | 30 days | 7/31/06 | 9/11/06 | 123 | 78 | |
78 | 1.10.2 | Detector Maintenance | 10 days | 9/12/06 | 9/25/06 | 77 | 79 | |
79 | 1.10.3 | PMD Maintenance Complete | 0 days | 9/25/06 | 9/25/06 | 78 | 145 | |
80 | 1.11 | EEMC Maintenance | 15 days | 9/14/06 | 10/4/06 | |||
81 | 1.11.1 | PMT/MAPMT Box Maintenance | 12 days | 9/14/06 | 9/29/06 | Mech.Tech.[2] | 69,112 | 82SS |
82 | 1.11.2 | Subsystem Testing | 15 days | 9/14/06 | 10/4/06 | 81SS | 83 | |
83 | 1.11.3 | EEMC Maintenance Complete | 0 days | 10/4/06 | 10/4/06 | 82 | 145,115 | |
84 | 1.12 | TPC Maintenance | 35.75 days | 7/21/06 | 9/11/06 | |||
85 | 1.12.1 | Remove East/West Bad FEE/RDO | 5 days | 7/21/06 | 7/28/06 | Electronic Tech[2] | 29 | 88 |
86 | 1.12.2 | Install East FEE/RDO | 5 days | 8/28/06 | 9/1/06 | Electronic Tech[2] | 55 | 89,87 |
87 | 1.12.3 | Install West FEE/RDO | 5 days | 9/5/06 | 9/11/06 | Electronic Tech[2] | 86 | 89,69 |
88 | 1.12.4 | Maintenance on Gas Room UPS | 1 day | 7/28/06 | 7/31/06 | 85 | 89 | |
89 | 1.12.5 | TPC Maintenance Complete | 0 days | 9/11/06 | 9/11/06 | 88,87,86 | 139,145,107 | |
90 | 1.13 | TOF Maintenance | 5 days | 10/5/06 | 10/11/06 | |||
91 | 1.13.1 | Remove Old Tray | 2 days | 10/5/06 | 10/6/06 | Mech.Tech. | 92 | |
92 | 1.13.2 | Install New Trays | 3 days | 10/9/06 | 10/11/06 | Mech.Tech. | 91 | 93 |
93 | 1.13.3 | TOF Installation Complete | 0 days | 10/11/06 | 10/11/06 | 92 | 115 | |
94 | 1.14 | FMS Installation | 43 days | 8/7/06 | 10/6/06 | |||
95 | 1.14.1 | Install FMS Carriages | 5 days | 8/7/06 | 8/14/06 | Mech.Tech.[2] | 40 | 96 |
96 | 1.14.2 | Install FMS Cells | 30 days | 8/14/06 | 9/26/06 | Mech.Tech.[2] | 95 | 98FF,97SS |
97 | 1.14.3 | Install AC Power | 5 days | 8/14/06 | 8/21/06 | Electrician[2] | 96SS | 100 |
98 | 1.14.4 | Install FMS Enclosures | 5 days | 9/19/06 | 9/26/06 | Mech.Tech.[2] | 96FF | 99 |
99 | 1.14.5 | Install FMS Cabling | 8 days | 9/26/06 | 10/6/06 | Mech.Tech.[2] | 98 | 101 |
100 | 1.14.6 | Install Electronics Racks | 10 days | 8/21/06 | 9/5/06 | Electronic Tech[2] | 97 | 101 |
101 | 1.14.7 | FMS Installation Complete | 0 days | 10/6/06 | 10/6/06 | 99,100 | 145 | |
102 | 1.15 | BBC Maintenance | 25 days | 7/6/06 | 8/10/06 | |||
103 | 1.15.1 | Subsystem Maintenance | 20 days | 7/6/06 | 8/3/06 | 5,9 | 104 | |
104 | 1.15.2 | Detector Commisioning | 5 days | 8/3/06 | 8/10/06 | 103 | 105 | |
105 | 1.15.3 | BBC Maintenance Complete | 0 days | 8/10/06 | 8/10/06 | 104 | ||
106 | 1.16 | Trigger Maintenance | 10 days | 9/12/06 | 9/25/06 | |||
107 | 1.16.1 | Trigger Maintenance | 10 days | 9/12/06 | 9/25/06 | 89 | 108 | |
108 | 1.16.2 | Trigger Maintenance Complete | 0 days | 9/25/06 | 9/25/06 | 107 | 145 | |
109 | 1.17 | Pole Tip Hose Replacement | 5 days | 7/31/06 | 8/4/06 | |||
110 | 1.17.1 | Remove Old Hose | 2 days | 7/31/06 | 8/1/06 | Mech.Tech.[2] | 123 | 111 |
111 | 1.17.2 | Install New Braided Hose | 3 days | 8/2/06 | 8/4/06 | Mech.Tech.[2] | 110 | 112 |
112 | 1.17.3 | Hose Replacement Complete | 0 days | 8/4/06 | 8/4/06 | 111 | 81 | |
113 | 1.18 | Magnet Power Supply Maintenance & Test | 87 days | 6/26/06 | 10/27/06 | |||
114 | 1.18.1 | Power Supply Maintenance & Test | 5 days | 6/26/06 | 6/30/06 | Electronic Tech[2] | 3SS | 5,36 |
115 | 1.18.2 | Remove East/West Scaffold | 0.5 days | 10/12/06 | 10/12/06 | Carpenter[2] | 83,93 | 116SS |
116 | 1.18.3 | Install East Pole Tip | 1 day | 10/12/06 | 10/12/06 | Mech.Tech.[2] | 115SS | 117 |
117 | 1.18.4 | Install West Pole Tip | 1 day | 10/13/06 | 10/13/06 | Mech.Tech.[2] | 116 | 118,143FF |
118 | 1.18.5 | Power Supply Maintenance & Test | 10 days | 10/16/06 | 10/27/06 | Electronic Tech[2] | 117 | 119 |
119 | 1.18.6 | Power Supply Maintenance Complete | 0 days | 10/27/06 | 10/27/06 | 118 | 146 | |
120 | 1.19 | C-AD Maintenance | 49 days | 7/24/06 | 9/29/06 | |||
121 | 1.19.1 | SGIS Modifications | 10 days | 9/18/06 | 9/29/06 | Elect.Tech.[2] | 130,144 | |
122 | 1.19.2 | PS Sound Barrier Wall | 10 days | 7/31/06 | 8/11/06 | 123 | ||
123 | 1.19.3 | AC Substation Maintenance | 5 days | 7/24/06 | 7/28/06 | 62,110,124,128,77,42,59,31,67,38,132,122 | ||
124 | 1.19.4 | Control Room Modification | 10 days | 7/31/06 | 8/11/06 | 123 | 126 | |
125 | 1.19.5 | Install West Tunnel Shielding | 5 days | 8/7/06 | 8/14/06 | Riggers[3] | 39 | |
126 | 1.19.6 | DAQ Room A/C Upgrade | 10 days | 8/14/06 | 8/25/06 | 124 | 127 | |
127 | 1.19.7 | Fire Sprinkler Preaction Upgrade | 10 days | 8/28/06 | 9/11/06 | 126 | 130 | |
128 | 1.19.8 | MCW Flow Balance | 10 days | 7/31/06 | 8/11/06 | Mech.Tech.[2] | 123 | 129 |
129 | 1.19.9 | Seal Tower Basin | 5 days | 8/14/06 | 8/18/06 | Mech.Tech.[2] | 128 | |
130 | 1.19.10 | C-A Maintenance Complete | 0 days | 9/29/06 | 9/29/06 | 127,121 | ||
131 | 1.20 | Connect Detector Utilities | 64 days | 7/31/06 | 10/27/06 | |||
132 | 1.20.1 | Connect Magnet LCW | 1 day | 7/31/06 | 7/31/06 | Mech.Tech.[2] | 29,123 | 133 |
133 | 1.20.2 | Install Buss Bridge | 0.5 days | 8/1/06 | 8/1/06 | Mech.Tech.[2] | 132 | 134,137 |
134 | 1.20.3 | Connect Electrical Power | 1 day | 8/1/06 | 8/2/06 | Electrician[2] | 133 | 135,136 |
135 | 1.20.4 | Connect Magnet Power | 1 day | 8/2/06 | 8/3/06 | Elect.Tech.[2] | 134 | |
136 | 1.20.5 | Connect All Subsystem Utilities | 1 day | 8/2/06 | 8/3/06 | Mech.Tech.[2] | 134 | |
137 | 1.20.6 | Connect Platform MCWS | 0.5 days | 8/1/06 | 8/1/06 | Mech.Tech. | 133 | 138 |
138 | 1.20.7 | Connect South Platform Stairs | 1 day | 8/2/06 | 8/2/06 | Mech.Tech.[2] | 137 | |
139 | 1.20.8 | Connect Vacuum Pipe & Supports | 3 days | 9/25/06 | 9/27/06 | Mech.Tech.[2] | 72,89 | 140SS |
140 | 1.20.9 | Vacuum Pipe Bake-out | 10 days | 9/25/06 | 10/6/06 | Mech.Tech.[2] | 139SS | 141 |
141 | 1.20.10 | Install START Detectors | 0.5 days | 10/9/06 | 10/9/06 | Mech.Tech. | 140 | 142 |
142 | 1.20.11 | Survey Beam Pipe | 2 days | 10/9/06 | 10/11/06 | Surveyors[2] | 141 | 143 |
143 | 1.20.12 | Install BBC Detectors | 1 day | 10/13/06 | 10/13/06 | Mech.Tech.[2] | 142,117FF | |
144 | 1.20.13 | Detector Safety Certification | 5 days | 10/2/06 | 10/6/06 | 121 | 145 | |
145 | 1.20.14 | Subsystems testing in WAH | 5 days | 10/9/06 | 10/13/06 | 144,65,108,101,72,79,83,89 | 146 | |
146 | 1.20.15 | Shutdown Activities Complete | 0 days | 10/27/06 | 10/27/06 | 145,119 |