Pre- and post-beam commissioning

Post-installation / pre-beam commissioning
  1. Pre-post checking, to make sure we are in same bin as BBC.  DONE
  2. Verify proper mapping from TUFF to StEvent (tests databases, cabling...)  ("Seven Patterns" test) DONE
  3. Vped adjustment   DONE
  4.  I-V scan has been done about once/day   DONE
  5. Confirm data goes from QT32C to TCU 
    • this is important for TRIGGER readiness, but not for PHYSICS readiness
    • Prashanth or Rosi need to write up the purpose and instructions here.


Post-beam commissioning to be ready for PHYSICS
  1. (Re-)confirm pre-post timing  (it's easy and it's important)
    • Same instructions as item #1 above.
  2. Timing scan    DONE
  3. Bias scan   DONE