Mechanical Structure

Speaker : Yi Yang, Han-sheng Li


Talk time : 09:50, Duration : 00:20

 

Simulation

Speaker : Te-Chuan Huang/Flemming Videbaek, Krishan Gopal


Talk time : 10:10, Duration : 00:20

 

STAR Forward Silicon Tracker Meeting

2019-12-12 09:30
2019-12-12 11:00
America/New York
Thursday, 12 December 2019
https://bluejeans.com/101020434 , at 14:30 (GMT), duration : 01:30
TimeTalkPresenter
09:30T-board, and Inner Signal Cable ( 00:20 ) 0 filesJianing Dong, Mike Capotosto, Gerard Visser
09:50Mechanical Structure ( 00:20 ) 1 fileYi Yang, Han-sheng Li
10:10Simulation ( 00:20 ) 0 filesTe-Chuan Huang/Flemming Videbaek, Krishan Gopal

eTOF data run 20344007 - 20334021

Runs 20334007, 008 and 013-021 combined give roughly 1.2M events with ETOF included.

Attached below are a few plots after basic position and T0 calibration and some thoughts:

Centrality and transverse momentum dependence of anisotropic flow of identified hadrons in Au+Au collisions at 200 GeV

TPC Meeting

2019-12-11 15:00
2019-12-11 16:00
America/New York
Wednesday, 11 December 2019
1-189, at 20:00 (GMT), duration : 01:00
TpcRS Altro4 threshold related issue: https://drupal.star.bnl.gov/STAR/blog/iraklic/tpcresponsesimulator-calibration

Meeting Location - 
BNL Room 1-189


The Bluejean connection

Title:  STAR TPC Weekly
Description: Weekly TPC meeting for the STAR Collaboration
Community: STAR

Phone Dial-in
+1.408.740.7256 (US (San Jose))
+1.888.240.2560 (US Toll Free)
+1.408.317.9253 (US (Primary, San Jose))

Meeting ID: 276 827 050

Direct link: https://bnl.bluejeans.com/276827050

Run 20 BTOW timing

From files Tonko supplied for run #20344042

Integral v2 study

 

December 2019 - EPD East and West timing is now different

Run15 pp200 Embedding -- 2019-12-10

 

HF PWG paper plans - 2019/12/12

 

191210-Output files for T-board (v3.0)

 Keep ONE set of temperature sensor and reset circuit

Geometry

Vped scans (Dec. 2019)

 Following Rosi's instructions (https://drupal.star.bnl.gov/STAR/blog/rjreed/epd-vped-scans-2019) and using run 20343004-8, and not running with the CAMAC crate off, I generated the attached PDFs

Diffractive pi^0 A_N with FMS and EEMC

T-Board V3.0 Prototype Cable Assembly

 

Pre-post checking using cosmics and BBC (Dec. 2019)

Work plan for installing the EPD

Each year, when the EPD team will mount the device, Rahul would like a workplan.  It is more or less the same each year.  Here is an image, and at the bottom are some files that you can modi

EPD Commissioning - Step-by-step

Useful links:

Weekly Meeting (Dec. 9)

 -Xiaoxuan, pAu calibration update